River Road Pavement Rehabiltation $1.3m (complete)

Pavement Rehabilitation and road re-alignment project
CLIENT: Waikato District Alliance 

Following the diversion of fibre, water and communication services, Schick undertook the most challenging aspect of the project, being the construction methodology to achieve the significant vertical realignment of the road comprising 3m deep bulk cut and 2.5m deep bulk fill. The project was programmed and completed in three main sections of pavement each 900m long.

 