00941

Hamilton West School Asphalt and Drainage Remediation $212,000 (complete)

Remediation of existing asphalt surfaced hard courts, access entrance and associated drainage
CLIENT: Ministry of Education c/- Hamilton West School BOT 

Remediation of existing asphalt surface hard courts, access entrance and associated drainage. The scope of work included uplifting existing surfacing, re-grading existing base course and adding base course to improve falls on the asphalt surfaces to ensure water run-off to new drainage.  

The new drainage works included supply and installation of a slot drain to the perimeter of the netball courts discharging to new and existing catch pits. Supply and installation of new storm water pipe work from the new and existing catch pits to an existing Hamilton City Council storm water manhole in the street.

 
1footer Civil Contractors New Zealand 1footer NZ Transport Agency
ISO9001-7131footer Site Safe Member
NZS4801-319
1footer Site-Wise-logo
1footer ACC Logo 1footer Canterbury Rebuild Charter
   

HEAD OFFICE

18 Manchester Place, Te Rapa Hamilton 3200
PO Box 20463, Te Rapa Hamilton 3241

EMAIL US    Follow us on Facebook