00938

River Road Pavement Rehabiltation $1.3m (complete)

Pavement Rehabilitation and road re-alignment project
CLIENT: Waikato District Alliance 

Following the diversion of fibre, water and communication services, Schick undertook the most challenging aspect of the project, being the construction methodology to achieve the significant vertical realignment of the road comprising 3m deep bulk cut and 2.5m deep bulk fill. The project was programmed and completed in three main sections of pavement each 900m long.

 
1footer Civil Contractors New Zealand 1footer NZ Transport Agency
Telarc QualityTelarc-14001 (1)1footer Site Safe Member 1footer Site-Wise-logo1footer ACC Logo1footer Canterbury Rebuild Charter
 

OUR PARTNERS

 

HEAD OFFICE

18 Manchester Place, Te Rapa Hamilton 3200
PO Box 20463, Te Rapa Hamilton 3241

EMAIL US    Follow us on Facebook