Project Details
Client
T2TM SH5/SH28 Harwoods Roundabout
Location
Tapapa, South Waikato
Value
$5.8 million
STATUS
Completed February 2026
The project involved construction of a new rural roundabout at the intersection of SH5 and SH28, together with extensive pavement reconstruction and widening, drainage upgrades, streetlighting, concrete works, signage and roadmarking.
Delivered entirely within a live State Highway environment, the works required detailed staging to maintain traffic movements throughout construction. With no suitable detour, temporary road or full closure available, Schick developed a comprehensive traffic management and construction methodology that enabled the intersection to remain operational while major pavement and infrastructure works were completed.
Pavement construction formed a significant part of the project, with approximately 9,000m² of new pavement constructed using stabilised subbase, TNZ Class 1 AP40 aggregate, deep lift asphalt and SMA surfacing. During construction, Schick identified discrepancies between the existing subgrade and design levels and worked collaboratively with the project team to develop and implement a revised solution, ensuring the long-term performance of the completed pavement.
The project also included approximately 750m of new stormwater pipeline and 31 drainage structures, 2.4km of kerbing, extensive concrete swales and traffic islands, and the detailed concrete construction of the central roundabout. Streetlighting infrastructure was upgraded, including the installation of 27 new streetlights and approximately 1.4km of streetlight cable.
Following strong performance during delivery, Schick was awarded an additional separable portion of works for the SH5 Midblock safety improvements. This extended the project scope to include approximately 1km of shoulder widening, pavement construction, drainage improvements and new roadside safety barriers.
Despite winter weather, complex staging and the challenges associated with construction under continuous live traffic, Schick completed the primary contract 12 working days ahead of the contractual completion date, on budget and with zero harm across 142 days on site.
Under a separable portion of the contract, Schick completed our first Hexloc wall installation, constructed along the road edge adjacent to a steep drop-off. The works required careful planning, with excavation triggering a 24/7 one-lane traffic operation. The team excavated approximately 427m³, placed 350m³ of bedding and backfill, installed subsoil drainage and completed a total of 334 blocks. Strong coordination between excavation, installation, backfilling and traffic management resulted in excellent productivity, with a best day of 94 blocks installed, exceeding the supplier’s previous best of 65 blocks in a day.
Works included:
- Construction of the new SH5/SH28 rural roundabout
- Approximately 9,000m² of pavement construction
- Stabilised subbase, aggregate and asphalt pavement construction
- Approximately 750m of stormwater pipeline and 31 drainage structures
- Approximately 2.4km of kerbing
- Concrete swales, splitter islands and central roundabout construction
- Installation of 27 new streetlights and associated infrastructure
- Signage, roadmarking and safety improvements
- Complex staging and traffic management within a live State Highway environment
- Additional SH5 Midblock shoulder widening and safety improvements