Boat Ramp and Sea Wall Repairs $627,000

Boat ramp and sea wall structural repairs

Project Details

Client

Waikato District Council

Value

$627,000

Status

Complete

The project involved working in and around sensitive coastal and river environments requiring detailed methodology and planning to achieve positive outcomes with no environmental impacts.

Schick was required to source, supply and install all materials required to complete the upgrades. 

Sites included:

  • Taupiri – clearing and earthwork, boat ramp construction – PVC sheet pile, basecourse and reinforced concrete
  • Raglan Sea Wall – timber pole wall including lagging, drainage, geotextile, backfill, precast panel concrete slabs
  • Puriri Park – grouted boulder wall (330 boulders were sourced and installed), and ramp protection, filter material, geotextile and drains
  • Te Akau – clearing and earthworks, grouted boulder wall and ramp protection
  • Manu Bay – grouted boulder wall and ramp protection