the-base-te-awa The Base, Te Awa (Stage 1A + 1B)
Client: Tainui Group Ltd                Scale: $7M

Earthworks and drainage for Stage 1A building works. Bulk excavation (20,000m³) of basement carpark below building. Installation of sub-surface drainage below building car park. Backfilling of perimeter walls, excavation and backfilling of access ramps.  Removal of asbestos contaminated soil, testing and removal of areas suspected of containing asbestos. Testing and removal of oil contaminated soil. High level of traffic management required due to live traffic situations. 
 
silver-fern-farms-siteworks Silver Fern Farms - Project Paragon 
Client: Ebert Construction Ltd             Scale: $1.7M

We were engaged to carry out siteworks and drainage in and around the new and existing building works following extensive fire damage to the existing plant. Workspace was at times very restrictive and working with other subcontractors in these areas proved a challenge. All works were complete with minimal disruption. Additional work to landscape the site (approx. $350K) was negotiated at completion of the main works.
 
waikato-hospital-landscaping Waikato Hospital Siteworks + Landscaping (2008 - 2010)
Client: Fletcher Building & Waikato DHB        Scale: $2.3M

Excavation and construction of roading, kerbing footpaths and pavements. Construction of retaining walls, timber and concrete 25 - 40m long, piping and guardrails. Concrete piles with structural guardrails on top. Black honed feature walls with cantilever timber slat seats. Feature paver bands and 2,000m² of concrete finishes. Bollards with timber slats, landscape planting trees and shrubs, lighting, irrigation system, strip drains, water feature wall, pump systems and bus shelters. Works completed to project programme.
 
summerset-retirement-village Summerset Retirement Village
Client: Summerset Retirement Villages NZ          Scale: $3M+

Civil works carried out for the construction of roading, drainage, earthworks and building platforms for a 50 unit retirement village including community facilities and landscaping. Works were completed in stages over a 3 year period and constructed to the highest finishing standards.
 
1footer Civil Contractors New Zealand 1footer NZ Transport Agency
Telarc QualityTelarc-14001 (1)1footer Site Safe Member 1footer Site-Wise-logo1footer ACC Logo1footer Canterbury Rebuild Charter
   

HEAD OFFICE

18 Manchester Place, Te Rapa Hamilton 3200
PO Box 20463, Te Rapa Hamilton 3241

EMAIL US    Follow us on Facebook