3 Waters Renewal – Waitomo District Council

A $2 million Waitomo District Council programme renewing water, wastewater and stormwater infrastructure across eight sites using trenching, drilling and relining.

Project Details

Client

Waitomo District Council

Location

Waitomo District

Value

$2 million

STATUS

In progress – due for completion December 2026

The 3 Waters Renewals contract involves the progressive renewal and upgrade of critical water, wastewater and stormwater infrastructure across eight sites throughout the Waitomo District.

The programme includes a combination of open trench construction, directional drilling and sewer relining, allowing the construction methodology to be tailored to the existing infrastructure, site conditions and surrounding environment.

Works include wastewater renewals on Hospital Road, John Mandeno Drive and King Street West, stormwater upgrades on Hospital Road and Awakino Road, and watermain renewals across Mōkau Township, William Street, Anzac Street, Matai Street and the Esplanade. Existing sewer mains on King Street East and George Street are also being rehabilitated through relining.

With works spread across multiple communities and programmed progressively through to 2027, delivery requires careful coordination and staging to maintain existing services and minimise disruption to residents and road users.

Works included:

  • Water, wastewater and stormwater infrastructure renewals
  • Open trench pipeline installation
  • Directional drilling of new watermains and rider mains
  • Rehabilitation and relining of existing sewer mains
  • Installation of stormwater culverts
  • Connections to existing live networks
  • Traffic and access management
  • Reinstatement of affected areas